A 2020 Capital Improvement Project, this project will improve surface and sub-surface drainage, construct a modern wash pad facility (photo), and spot-treat pavement failures at the Championship Golf Maintenance Building, adjacent to the chipping green. This project addresses health and safety issues and will prevent future water damage to this facility. A local engineering consultant completed the design, and the construction contract was awarded to Cruz Construction at the June 23, 2020 Board of Trustees meeting. 

Cruz Construction Contract Status:

Original

Contract Amount

Change Orders

Current Total Contract Amount

Total Payments for Work Completed to Date

Current Balance to Completion (including retainage)

$425,433

$66,517

$491,950

$464,977

$26,973