Updated July 8, 2022

Burnt Cedar Swimming Pool Improvements Project – 3970BD2601

A 2021 Capital Improvement and Board of Trustees Priority Project, this project will reconstruct the two (2) existing pools (full size and toddler) at Burnt Cedar Beach, which were originally constructed in 1968.

This project requires complete closure of the pool and pool deck for the entire 2021 season, but residents can still enjoy use of the beach, picnic areas, and bar amenities at the site during construction.

Download the Burnt Cedar Drawing/Plan Set (PDF)

Download the Project Summary data sheet (PDF)

The new pool will be wider, to accommodate an additional 6th swim lane. The orientation of the pool has been modified to showcase the site’s incredible Tahoe views. Kids are sure to spend hours enjoying the pool slide, and the wading pool will be very popular with its new fun water feature. The renovations will provide a modern, quality facility for Incline Village that will also include a raised terrace for dining and a new pedestrian path connecting the west parking area to the sandy beach and picnic areas.

Design of the pool was completed in early 2021, with a design team including TSK Architects, Aquatics Design Group, RCI, Inc., Design Workshop, Nelson-Wilcox Structural Engineers and MSA, Inc.

CORE West, Inc. was selected as the Construction Manager at Risk (CMAR) and mobilized to the site to start work on May 3, 2021. Construction is on schedule, with all outside work currently buttoned up for the winter season. The contractor will return mid-January to continue working on piping and equipment installation inside the mechanical room.

Completion is on track for June 2022, just in time for residents and their guests to enjoy the new facility for the summer season.

Construction Photos

Photos below were taken in April 2022

deck concrete work

walkway concrete work

Concrete work on decking

deck concrete work

deck concrete work

Burnt Cedar pool project concrete deck install

 

Photos below were taken in November and December 2021

Burnt Cedar pool project in winter

Burnt Cedar pool project pump house

Burnt Cedar pool project walkway

Burnt Cedar pool project landscaping

Burnt Cedar pool project in winter view

 

Photos below were taken in August 2021

Top to bottom: Wading pool rebar and concrete installation, main pool concrete and stairs installation.

Wading Pool Rebar

Wading Pool Progress 1

Wading Pool Progress 2

Pool Stairs

pool concrete fill

 

Photos below were taken in June and July 2021

Top to bottom: Site compaction, rock breaking operations, new pool forms and excavation, new pool piping and shotcrete installation.

Pool Compaction

Pool Compaction

Rock Hammer

Pool Forms

New Pool Excavation

New Pool Piping

New Pool Shotcrete

 

Update from June 9, 2021

CORE Construction was selected as the Construction Manager at Risk (CMAR) and mobilized to the site May 3, 2021. CORE has installed all the required BMPs, have altered the parking lot to allow easy access to the sandy beach and picnic areas, and started the demolition phase of the pool, toddler pool and pool deck. (See photos of the demolition below.) CORE will be working on installation of the pool piping throughout the month of June. 

 

May 2021 Demolition Photos

Top to bottom: The empty Burnt Cedar pool before demolition began, during the demolition process, and after demolition is complete, followed by the the wading/kiddie pool demolition.

Burnt Cedar Pool before demolition

Burnt Cedar Pool Deck demolition

Burnt Cedar Pool demolition

Burnt Cedar Pool post demolition

Wading Pool demolition

Wading Pool post demolition