2021 Burnt Cedar Swimming Pool Improvements Project
Updated July 8, 2022
Burnt Cedar Swimming Pool Improvements Project – 3970BD2601
A 2021 Capital Improvement and Board of Trustees Priority Project, this project will reconstruct the two (2) existing pools (full size and toddler) at Burnt Cedar Beach, which were originally constructed in 1968.
This project requires complete closure of the pool and pool deck for the entire 2021 season, but residents can still enjoy use of the beach, picnic areas, and bar amenities at the site during construction.
Download the Burnt Cedar Drawing/Plan Set (PDF)
Download the Project Summary data sheet (PDF)
The new pool will be wider, to accommodate an additional 6th swim lane. The orientation of the pool has been modified to showcase the site’s incredible Tahoe views. Kids are sure to spend hours enjoying the pool slide, and the wading pool will be very popular with its new fun water feature. The renovations will provide a modern, quality facility for Incline Village that will also include a raised terrace for dining and a new pedestrian path connecting the west parking area to the sandy beach and picnic areas.
Design of the pool was completed in early 2021, with a design team including TSK Architects, Aquatics Design Group, RCI, Inc., Design Workshop, Nelson-Wilcox Structural Engineers and MSA, Inc.
CORE West, Inc. was selected as the Construction Manager at Risk (CMAR) and mobilized to the site to start work on May 3, 2021. Construction is on schedule, with all outside work currently buttoned up for the winter season. The contractor will return mid-January to continue working on piping and equipment installation inside the mechanical room.
Completion is on track for June 2022, just in time for residents and their guests to enjoy the new facility for the summer season.
Construction Photos
Photos below were taken in April 2022
Photos below were taken in November and December 2021
Photos below were taken in August 2021
Top to bottom: Wading pool rebar and concrete installation, main pool concrete and stairs installation.
Photos below were taken in June and July 2021
Top to bottom: Site compaction, rock breaking operations, new pool forms and excavation, new pool piping and shotcrete installation.
Update from June 9, 2021
CORE Construction was selected as the Construction Manager at Risk (CMAR) and mobilized to the site May 3, 2021. CORE has installed all the required BMPs, have altered the parking lot to allow easy access to the sandy beach and picnic areas, and started the demolition phase of the pool, toddler pool and pool deck. (See photos of the demolition below.) CORE will be working on installation of the pool piping throughout the month of June.
May 2021 Demolition Photos
Top to bottom: The empty Burnt Cedar pool before demolition began, during the demolition process, and after demolition is complete, followed by the the wading/kiddie pool demolition.